Electrification of Line no. 293 Šumperk – Kouty nad Desnou
Client: Svazek obcí údoly Desné
Technical data, description:
Reconstruction of track substructure and superstructure, road buildings, new construction of OCL direct system 3 kV DC, new construction of traction substations 22kV AC / 3 kV DC, reconstruction of signaling and communication equipment, reconstruction of lighting and heavy current distribution, establishment of electrical heating switches system.
Total investment costs: CZK 199 911 725 (excl. VAT)
Realization date: IV/2015 – XI/2015