Complete reconstruction of the traction transformer station Mýto
Client: SŽDC, s.o.
Investor: SŽDC, s.o.
Technical data, description:
The complete reconstruction of the Mýto traction transformer station is a part of the construction of the Third Railway Corridor of selected network of railway lines, specifically building “Optimization of the Line Zbiroh – Rokycany”. The project included the following: reconstruction of outside substation technology (123 kV), including control and supervision system, supply and installation of single-phase transformers 123/27.5 kV (covered design), supply and installation of a 27.5 kV AC substation (cabinet design), including control and supervision system, supply and installation of filtration/compensation equipment, reconstruction of own consumption and supervisory system technology, incl. resulting modifications at the electrical control room in Pilsen. The project also included the reconstruction of supply/return cabling and its connection to the simultaneously reconstructed overhead contact lines for the open track Holoubkov – Rokycany.
Total investment costs: CZK 97 625 523 (excl. VAT)
Realization date: IV/2011 – XI/2011