Line 308 Hranice na Moravě – Střelná, Section Valašské Meziříčí (excl.) – Jablůnka (excl.) and Vsetín (excl.) – Horní Lideč (excl.)
Technical data, description:
Reconstruction of overhead contact lines and rail-earthing of a 3 kV DC system for dual-track line Hranice na Morave – Horní Lideč, reconstruction of outside lighting and cable lines – low voltage and 6 kV, modification of distribution transformer station technology 22/0.4 kV in Nz. Bystřička.
Total investment costs: CZK 130 311 442 (excl. VAT)
Realization date: IX/2015 – VIII/2016