Client: Metrostav
Technical data, description:
Reconstruction of overhead contact lines and rail-earthing of a 3 kV DC system for dual-track line Praha Holešovice – Praha Bubeneč, in Praha Holešovice railway station and at branch line Stromovka Bubny, reconstruction of outside lighting and low voltage cable lines in Praha Holešovice railway station and new station Podbaba, reconstruction of remote control of disconnectors and high-voltage lines (6 kV) for track section, modification of the 6 kV substation technology and low-voltage substation in Praha Holešovice railway station.
Total investment costs: CZK 94 878 459(excl. VAT)
Realization date: I/2013 – I/2016